Construction of 2,000 Mega Watt Subansiri lower dam project achieves elevation level, says Power Ministry

Construction of 2,000 Mega Watt Subansiri lower dam project achieves elevation level, says Power Ministry

On completion, the Subansiri Lower Hydroelectric Project will generate approximately 7,500 million kilowatt-hours of power annually, in a 90 percent-dependable year.

Advertisement
Construction of 2,000 Mega Watt Subansiri lower dam project achieves elevation level, says Power Ministry2,000 Mega Watt Subansiri lower dam

The construction of the 2,000 Mega Watt Subansiri Lower Hydroelectric Project dam has achieved Elevation Level (EL), said an official statement from Power Ministery on June 30.

The dam is located in Arunachal Pradesh and Assam and is being executed by NHPC Limited. 

''The construction of dam till the top level of Elevation Level (EL) 210 M has been completed in all blocks on June 29, 2023,'' the statement added. 

The Union Minister for Power and New & Renewable Energy R K Singh had, on May 31, 2023, reviewed the progress of the project, at which time it was informed that the project had achieved significant progress in dam concreting, with 14 blocks having achieved the top level of 210 meters and the remaining two blocks slated to be completed by June 2023.

NHPC has informed that more than 90 per cent of the total work of the project has already been completed. 

''The construction of all major components, including the Dam, Power House, and Hydromechanical Works is fast progressing towards completion. The remaining work of radial gates will be completed after the monsoon season and electricity generation is expected to begin by the end of Financial Year (FY) 2023-24,'' the statement read further.

On completion, the Subansiri Lower Hydroelectric Project will generate approximately 7,500 million kilowatt-hours of power annually, in a 90 percent-dependable year.

NHPC Limited commenced construction work of the Subansiri Lower Hydroelectric Project in January 2005 after obtaining forest clearance on October 12, 2004. However, due to agitations and protests by local stakeholders, the project construction work was stalled from December 2011 to October 2019. 

The project construction resumed on October 15, 2019, after the clearance by National Green Tribunal.

Also read: Arunachal: AAC chairperson Toko Sheetal to contest Lok Sabha elections against Kiren Rijiju

Edited By: Amit Chaurasia
Published On: Jun 30, 2023
POST A COMMENT