Mizoram: Bairabi–Sairang railway line gets green light for train operations

Mizoram: Bairabi–Sairang railway line gets green light for train operations

Train operations have been allowed on the newly laid track between Bhairabi and Hortoki, part of the Bairabi–Sairang New Line Railway Project that will connect Mizoram's capital Aizawl to the railway network, an official statement said on Friday.

Advertisement
Mizoram: Bairabi–Sairang railway line gets green light for train operationsBairabi–Sairang railway line gets green light for train operations

Train operations have been allowed on the newly laid track between Bhairabi and Hortoki, part of the Bairabi–Sairang New Line Railway Project that will connect Mizoram's capital Aizawl to the railway network, an official statement said on Friday. 

Commissioner of Railway Safety (CRS) Sumeet Singhal authorised the operation of freight and passenger trains on the 16.725 km broad gauge line between Bairabi and Hortoki on Thursday. 

The CRS completed the statutory inspection of the section at the end of last month, a Northeast Frontier Railway (NFR) release said. 

This section is part of the 51.38 km-long Bhairabi-Sairang project, with over 90 per cent physical progress already achieved. 

The new line between Bhairabi and Sairang is divided into four sections: Bhairabi–Hortoki, Hortoki–Kawnpui, Kawnpui–Mualkhang and Mualkhang–Sairang. 

Also Read: Mizoram highway blockade: Vehicle owners protest NH-306's poor condition

The CRS has approved train operations through the newly laid line at a maximum speed of 75 km per hour after a successful inspection and speed trial, the statement said. 

The newly laid BG line section has 20 major bridges and 27 minor bridges. 

There are 13 tunnels in this new section. The Bhairabi–Hortoki section has been constructed for train operation at a maximum speed of 100 km per hour on the main line and 30 km per hour on loop lines. 
The Bhairabi-Sairang railway project involves multiple tunnels and bridges in tough terrains, with the total length of tunnels in the project being 12,853 meters. 

The entire project will have a total of 55 major bridges and 89 minor bridges.

 On completion, the new rail line project will provide enhanced connectivity to the people of Mizoram, help grow small-scale industries in the area and boost tourism in the state, the statement said.

Edited By: Atiqul Habib